Salem County Construction Detours
NJ DOT Construction Updates
(Link leaves this website)
Road Closure: Commissioner's Pike, County Road 681
closed between Witt Road and Wister's Mill development for 7 months beginning 6/7/04 for construction of Kelly Saw Mill Bridge.
PLEASE BE ALERT IN WORK ZONE
New Bridge Closed in Lower Alloways Creek Township
The County anticipates that the bridge will be out of service till further notice.
Quinton Bridge, Quinton Twp, Route 49
Start construction February 2003, Completion date May 2005
Construction begins with preparation for construction of a temporary bridge structure
Rt. 49 will NOT be detoured during construction.
CR653 Acton Station Road and CR581 Quinton-Alloway Road WILL be detoured at their respective southern terminus' beginning on or about March 5, 2003 for a period of approximately two years.
PLEASE BE ALERT IN WORK ZONE
Penns Neck Bridge, Salem City, Route 49
Start construction February 2003, Completion date July 2005
NO detour during project.
PLEASE BE ALERT IN WORK ZONE